Augel built a fire water basin for the company SGL Carbon from Bonn in autumn 2015. To secure and fix the large excavation pit, we used an enormously heavy slide rail shoring with a span of 10 meters, which enabled us to excavate deeply and widely.

Projektleiter: Dirk Wassong, Augel
Bauherr: SGL Carbon
Ort der Ausführung: Bonn
Ausführungszeit: Herbst 2015 über einen Zeitraum von ca. 4 Monaten
Mannschaft: 5-10 Leute

As a result of this, and due to accurate work, we were able to install the large precast concrete elements even in the narrow conditions of the industrial plant.

Chronology
Of the Project

Breaking up the surface (concrete and asphalt)


Earthwork including insertion of an enormously heavy slide rail shoring with a span of 10 metres

Delivery and installation of the precast concrete elements

Leak Test


Connecting
the required cables

Backfilling of the exavation pit


Restoring the surface