Turnkey extension of a production and storage hall
Fermit GmbH

In 2015 Augel was commissioned by Fermit GmbH with the turnkey extension of a production and storage hall. Our complete solution included all services for the turnkey handover of the hall - from deconstruction and earthworks, reinforced concrete work and hall construction, to the installation of doors, gates, windows and light bands.

Project manager: Dirk Schmitt, Augel
Client: Fermit GmbH
Place of execution: Vettelschoß
Team: 8 - 15 People
Execution time: May 2015 – October 2015
Partner: Thermodo, Condulith (industrial floor), Atlas (hall construction)

The construction work was carried out in an environment heavily vegetated with trees. A particular challenge in this construction project was therefore to clear the construction site prior to the breeding and nesting season (June - October) in order not to disturb the natural life cycle of the birds.

Titel
Chronology
Of the Project

Short Facts

  • Engineering Services
  • Demolition and excavation work
  • Non-destructive asbestos disposal
  • Drainage
  • Reinforced Conrete
  • Industrial floor
  • Hall construction