New construction of a cycle and footpath bridge
as well as new cycle path
Pipeline Construction
B257 GRW Ahrbrück New replacement building
New construction of a cycle and footpath bridge
as well as new cycle path
Services
B257 GRW Ahrbrück New replacement building
New construction of a cycle and footpath bridge
as well as new cycle path
Services
B257 GRW Ahrbrück New replacement building
New construction of a cycle and footpath bridge
as well as new cycle path
Careers
B257 GRW Ahrbrück New replacement building
New construction of a cycle and footpath bridge
as well as new cycle path
Responsible
B257 GRW Ahrbrück New replacement building
New construction of a cycle and footpath bridge
as well as new cycle path
Bauen im sensiblen Industrie Bestand
B257 GRW Ahrbrück New replacement building
New construction of a cycle and footpath bridge
as well as new cycle path
Bauen im sensiblen Industrie Bestand
B257 GRW Ahrbrück New replacement building
New construction of a cycle and footpath bridge
as well as new cycle path
German Brand Award 21 special
B257 GRW Ahrbrück New replacement building
New construction of a cycle and footpath bridge
as well as new cycle path

In the summer of 2018, AUGEL was commissioned by LBM Cochem to build a 24-metre-long cycle and footpath bridge to cross the Ahr. The construction project also included the new construction of a 120-metre-long cycle path along the Ahr river in order to integrate the new bridge into the existing cycle path. Due to the new construction of the bridge, the cycle path, which originally ran along a main road, could be relocated to the former Ahr valley railway line.

Bauherr: LBM Cochem
Ort der Ausführung: 53506 Ahrbrück
Ausführungszeit: August 2018 – Juni 2019
Partner: IBS-Ingenieure BgR

The project was executed in the FFH nature reserve and therefore required the use of environmentally friendly materials and bio-oil operated machines.

Titel
Chronology
Of the Project
Augel-2020-089-RMR-Vörde
Approval procedure

Approval procedure (work in FFH nature reserve)

Setting up the construction site

Electric fishing in the construction area (by the nature conservation authority)

Augel-2020-089-RMR-Vörde
Construction of an open dewatering system

Construction of an open dewatering system to keep the excavation pit free of water and to discharge the pumped water

Earthworks for the construction of the foundation

Augel-2020-089-RMR-Vörde
Betonarbeiten

Concrete work for the construction of the for the construction of the central pillar

Concrete work for the construction of the east and west abutments Ost und West

Augel-2020-089-RMR-Vörde
Delivery of the bridge

May 16, 2019, 2.00 a.m.
Delivery of the bridge by heavy transport

Augel-2020-089-RMR-Vörde
Placing the bridge

Placing the bridge on the abutments

Augel-2020-089-RMR-Vörde
Construction of the 120-metre-long Ahr cycle path

Construction of the 120-metre-long Ahr cycle path to integrate the new bridge into the existing cycle path

Returning soils and areas to their natural state including armourstones and planting

Augel-2020-089-RMR-Vörde

A BRIDGE "FLOATS" TO ITS DESTINATION