Scroll
Zukunftsorientierte Komplettlösungen
Renovation of a plant line
For a production plant
of Wacker Chemie, Munich
Pipeline Construction
Renovation of a plant line
For a production plant
of Wacker Chemie, Munich
Services
Renovation of a plant line
For a production plant
of Wacker Chemie, Munich
Services
Renovation of a plant line
For a production plant
of Wacker Chemie, Munich
Careers
Renovation of a plant line
For a production plant
of Wacker Chemie, Munich
Responsible
Renovation of a plant line
For a production plant
of Wacker Chemie, Munich
Bauen im sensiblen Industrie Bestand
Renovation of a plant line
For a production plant
of Wacker Chemie, Munich
Bauen im sensiblen Industrie Bestand
Renovation of a plant line
For a production plant
of Wacker Chemie, Munich
German Brand Award 21 special
Renovation of a plant line
For a production plant
of Wacker Chemie, Munich

Within a time frame of only two weeks, Augel GmbH installed 470 m² of ultra-high strength ingbeton.During the renovation of a plant sump for a production plant of Wacker Chemie AG, Munich, at the Nünchritz site in Saxony, the construction company, together with its contractor, BGS GmbH, which specialises in the sealing of expansion joints, was in operation for just 4.5 weeks. The rehabilitation of the catchment basin was carried out during ongoing plant operation in the chemical plant. während des laufenden Anlagenbetriebs im Chemiewerk.

Projektleiter: Carsten Thiede
Bauherr: Wacker Chemie AG, München
Ort der Ausführung: Nünchritz, Sachsen
Partner: ingebton
logo-ingebton

The outstanding partnership between Wacker Chemie AG and the contractors Augel and BGS made it possible to complete the rehabilitation project in Nünchritz quickly and smoothly. Wacker Chemie AG's employees managed the coordination of the various trades involved independently, thus laying the foundations for a scheduled and completely trouble-free renewal of the plant's sump.

The biggest advantage: production could be continued throughout the entire refurbishment measures.

24h365
Titel
Chronology
Of the Project
Augel-2020-089-RMR-Vörde
Building site equipment

Coating work on rising walls

Augel-2020-089-RMR-Vörde
Construction of an open dewatering system

Installation of approx. 470 m² of ultra high strength ingbeton in a total of 198 individual areas on existing screed layer

Augel-2020-089-RMR-Vörde
Betonarbeiten

Installation of 700 metres of WHG joints type PE-Seal (a type of joint specially designed for use in LAU systems, which harmonises perfectly with the industrial floor)

Augel-2020-089-RMR-Vörde

THE NÜNCHRITZ PLANT

has been one of Wacker Chemie AG's sites since 1998. In Nünchritz, Wacker produces silicon-based chemicals. The Group pays particular attention to environmental protection and sustainability: All production plants form a highly integrated network system for maximum conversion of raw materials into target products. For this reason, the fastest possible refurbishment of a production plant's catchment basin was initiated with an AwSV (Ordinance on Systems for Handling Substances Hazardous to Water) sealing layer.