Scroll
Zukunftsorientierte Komplettlösungen
Complete Renewal
of a fuel-tight
Drainage
AFS Aviation Fuel Services GmbH
Pipeline Construction
Complete Renewal
of a fuel-tight
Drainage
AFS Aviation Fuel Services GmbH
Services
Complete Renewal
of a fuel-tight
Drainage
AFS Aviation Fuel Services GmbH
Services
Complete Renewal
of a fuel-tight
Drainage
AFS Aviation Fuel Services GmbH
Careers
Complete Renewal
of a fuel-tight
Drainage
AFS Aviation Fuel Services GmbH
Responsible
Complete Renewal
of a fuel-tight
Drainage
AFS Aviation Fuel Services GmbH
Bauen im sensiblen Industrie Bestand
Complete Renewal
of a fuel-tight
Drainage
AFS Aviation Fuel Services GmbH
Bauen im sensiblen Industrie Bestand
Complete Renewal
of a fuel-tight
Drainage
AFS Aviation Fuel Services GmbH
German Brand Award 21 special
Complete Renewal
of a fuel-tight
Drainage
AFS Aviation Fuel Services GmbH

Between November 2019 and July 2020, Augel renewed the complete fuel-tight drainage system of the tank terminal at Düsseldorf Airport and subsequently replaced the separator system. The entire work was done in compliance with WHG and was carried out by Augel itself.

Projektleiter: Michael Adams, Augel
Bauherr: AFS Aviation Fuel Services GmbH
Ort der Ausführung: Flughafen Düsseldorf
Ausführungszeit: November 2019 – Juli 2020

Continuous operation was guaranteed during the work. This construction project posed a special challenge, as more than 80, 100 tonne kerosene wagons arrive and depart every day. Therefore, the construction site was divided into 6 individual construction sections, of which no more than 2 construction sections were allowed to be open at the same time. In this way the kerosene cars could be refuelled at any time.

To ensure that no drip losses from refuelling reach open trenches, a 295-metre long ad hoc protective wall was also installed, which diverted drip losses into the old stock until the plant was completely renewed.

Titel
Chronology
Of the Project
Augel-2020-089-RMR-Vörde
Building site equipment

Planning by engineering office and preparation of the bill of quantities

Construction licensing procedure

Building site equipment

Augel-2020-089-RMR-Vörde
Entwässerung Rohre

Gradual Removal of the old and installation of the new drainage

Concreting of the individual pipeline sections with fuel-tight WHG concrete (incl. B2 monitoring)

Shoring work with slide rail shoring including previous statics

Augel-2020-089-RMR-Vörde
Abscheideranlage

Delivery and relocation of the separator system

Switching from old to new separator system alte zu neue Abscheideranlage

Removal of the old separator

Concreting in the area of the old and new separator

Augel-2020-089-RMR-Vörde
Parking space restoration

Jointing of all newly installed floor slab sections according to WHG

Water Resources Act Documentation with various proofs of welding work etc.

Augel-2020-089-RMR-Vörde